| Período | Valor Contratado Obra | Gastos Base Caixa | Saldo a Pagar Obra | |||||
|---|---|---|---|---|---|---|---|---|
| INCC | ME'S | Total INCC | R$ Reajustado | No Mês INCC | No Mês R$ | INCC | R$ Corrigido | |
| TOTAL = | 99.890 | - | 99.890 | 124.513.593 | 28.034 | 33.206.784 | 71.856 | 91.306.809 |
| PRÉ-OBRA | 99.890 | - | 99.890 | 109.118.793 | 2.630 | 2.844.820 | 97.259 | 106.273.973 |
| 1 · abr/24 | 99.890 | - | 99.890 | 109.415.726 | 624 | 684.273 | 96.635 | 105.886.633 |
| 2 · mai/24 | 99.890 | - | 99.890 | 109.961.810 | 1.138 | 1.253.645 | 95.497 | 105.179.072 |
| 3 · jun/24 | 99.890 | - | 99.890 | 110.868.838 | 850 | 944.270 | 94.647 | 105.141.831 |
| 4 · jul/24 | 99.890 | - | 99.890 | 111.620.333 | 454 | 508.470 | 94.192 | 105.384.856 |
| 5 · ago/24 | 99.890 | - | 99.890 | 112.382.255 | 557 | 628.127 | 93.635 | 105.518.650 |
| 6 · set/24 | 99.890 | - | 99.890 | 113.118.131 | 762 | 864.974 | 92.873 | 105.389.552 |
| 7 · out/24 | 99.890 | - | 99.890 | 113.733.227 | 514 | 586.446 | 92.359 | 105.418.202 |
| 8 · nov/24 | 99.890 | - | 99.890 | 114.451.040 | 581 | 667.623 | 91.778 | 105.468.392 |
| 9 · dez/24 | 99.890 | - | 99.890 | 114.869.088 | 519 | 598.394 | 91.259 | 105.288.046 |
| 10 · jan/25 | 99.890 | - | 99.890 | 115.399.395 | 463 | 536.304 | 90.797 | 105.282.050 |
| 11 · fev/25 | 99.890 | - | 99.890 | 116.269.228 | 614 | 718.263 | 90.182 | 105.433.619 |
| 12 · mar/25 | 99.890 | - | 99.890 | 116.689.387 | 439 | 515.011 | 89.744 | 105.338.768 |
| 13 · abr/25 | 99.890 | - | 99.890 | 117.103.195 | 465 | 547.388 | 89.279 | 105.205.188 |
| 14 · mai/25 | 99.890 | - | 99.890 | 117.645.654 | 1.119 | 1.325.426 | 88.160 | 104.422.221 |
| 15 · jun/25 | 99.890 | - | 99.890 | 118.250.873 | 1.043 | 1.242.728 | 87.117 | 103.784.712 |
| 16 · jul/25 | 99.890 | - | 99.890 | 118.963.664 | 1.762 | 2.114.107 | 85.354 | 102.383.396 |
| 17 · ago/25 | 99.890 | - | 99.890 | 119.899.319 | 1.336 | 1.617.477 | 84.018 | 101.701.573 |
| 18 · set/25 | 99.890 | - | 99.890 | 120.423.172 | 1.315 | 1.600.309 | 82.703 | 100.625.117 |
| 19 · out/25 | 99.890 | - | 99.890 | 120.591.969 | 1.219 | 1.485.356 | 81.484 | 99.308.558 |
| 20 · nov/25 | 99.890 | - | 99.890 | 120.886.045 | 1.307 | 1.597.339 | 80.177 | 98.005.296 |
| 21 · dez/25 | 99.890 | - | 99.890 | 121.148.786 | 1.688 | 2.069.008 | 78.489 | 96.199.029 |
| 22 · jan/26 | 99.890 | - | 99.890 | 121.347.207 | 1.413 | 1.735.670 | 77.076 | 94.661.780 |
| 23 · fev/26 | 99.890 | - | 99.890 | 122.031.257 | 1.087 | 1.345.031 | 75.989 | 94.000.799 |
| 24 · mar/26 | 99.890 | - | 99.890 | 122.293.038 | 943 | 1.169.358 | 75.046 | 93.093.222 |
| 25 · abr/26 | 99.890 | - | 99.890 | 122.795.847 | 1.661 | 2.071.282 | 73.385 | 91.524.749 |
| 26 · mai/26 | 99.890 | - | 99.890 | 123.711.035 | 710 | 893.773 | 72.676 | 91.546.164 |
| 27 · jun/26 | 99.890 | - | 99.890 | 124.513.593 | 820 | 1.041.913 | 71.856 | 91.306.809 |
| Grupo | Orçamento Base | ME'S | Orçamento c/ ME'S | Gastos Caixa | % Base INCC | Avanço Físico com D.I. | Variação do Custo | Saldo Contratual Corrigido | ||
|---|---|---|---|---|---|---|---|---|---|---|
| R$ - I0 | R$ Reajustado | No Mês | Acumulado | |||||||
| OBRA GERAL + TAXA ADM | 105.525.44499.890 incc's | -0 incc's | 105.525.44499.890 incc's | 124.513.452 | 1.041.913 | 33.207.46328.035 incc's | 28,07% | 91.305.988 | ||
| OBRA GERAL | 93.398.35188.410 incc's | -0 incc's | 93.398.35188.410 incc's | 109.974.696 | 1.041.913 | 32.081.68727.111 incc's | 30,66% | 15,67% | −15,00% | 77.893.010 |
| OBRA MALL + TAXA ADM | 40.981.24738.793 incc's | -0 incc's | 40.981.24738.793 incc's | 48.026.203 | 720.437 | 15.996.81213.586 incc's | 35,02% | 32.029.391 | ||
| OBRA MALL | 37.215.92835.228 incc's | -0 incc's | 37.215.92835.228 incc's | 35.898.147 | 720.437 | 15.996.81213.586 incc's | 38,57% | 21,33% | −17,24% | 27.500.339 |
| Custos Indiretos | 6.239.774 | - | 6.239.774 | 7.251.592 | 92.311 | 2.722.923 | 39,66% | 23,20% | −16,46% | 4.528.668 |
| Mov. Terra / Fundação / Contenção | 2.994.403 | - | 2.994.403 | 2.884.704 | 233.942 | 7.994.033 | 241,86% | 97,06% | −144,79% | - 5.109.329 |
| Shopping | 27.231.751 | - | 27.231.751 | 32.458.730 | 394.184 | 5.279.856 | 17,02% | 13,16% | −3,87% | 27.178.874 |
| Custos Adicionais | 750.000 | - | 750.000 | 902.125 | 902.125 | |||||
| Gastos Não Apropriados | - | - | - | - | - | |||||
| Remunerações e Contingências | 3.765.3193.564 incc's | -0 incc's | 3.765.3193.564 incc's | 4.529.052 | - | -0 incc's | 4.529.052 | |||
| Remunerações | 3.765.319 | - | 3.765.319 | 4.529.052 | 4.529.052 | |||||
| OBRA TORRES + TAXA ADM | 64.544.19761.097 incc's | -0 incc's | 64.544.19761.097 incc's | 76.487.249 | 321.476 | 17.210.65114.448 incc's | 23,65% | 59.276.598 | ||
| OBRA TORRES | 56.182.42353.182 incc's | -0 incc's | 56.182.42353.182 incc's | 66.477.545 | 321.476 | 16.084.87413.524 incc's | 25,43% | 11,92% | −13,51% | 50.392.671 |
| Custos Indiretos | 8.535.420 | - | 8.535.420 | 9.906.686 | 115.028 | 4.274.626 | 45,14% | 23,20% | −21,94% | 5.632.060 |
| Mov. Terra / Fundação / Contenção | 4.096.061 | - | 4.096.061 | 4.226.370 | 127.434 | 10.265.619 | 222,58% | 97,06% | −125,51% | - 6.039.249 |
| Estrutura | 9.630.651 | - | 9.630.651 | 11.550.270 | 78.846 | 1.344.054 | 11,89% | −11,89% | 10.206.216 | |
| Alvenaria/Fechamento | 2.469.396 | - | 2.469.396 | 2.970.272 | 168 | 168 | 0,01% | −0,01% | 2.970.105 | |
| Impermeabilização e Tratamentos | 613.909 | - | 613.909 | 738.106 | - | 17.651 | 2,43% | −2,43% | 720.455 | |
| Revestimentos Internos | 5.015.819 | - | 5.015.819 | 6.033.196 | 6.033.196 | |||||
| Revestimento Externo | 4.093.531 | - | 4.093.531 | 4.923.836 | 4.923.836 | |||||
| Esquadrias | 6.147.120 | - | 6.147.120 | 7.393.962 | 7.393.962 | |||||
| Pinturas | 823.839 | - | 823.839 | 990.941 | 990.941 | |||||
| Granitos e Pedras | 484.796 | - | 484.796 | 583.129 | 583.129 | |||||
| Instalações | 11.205.331 | - | 11.205.331 | 13.472.227 | - | 182.758 | 1,40% | 0,56% | −0,84% | 13.289.470 |
| Serviços Complementares | 1.126.882 | - | 1.126.882 | 1.355.451 | 1.355.451 | |||||
| Custos Adicionais | 1.939.669 | - | 1.939.669 | 2.333.099 | 2.333.099 | |||||
| Gastos Não Apropriados | - | - | - | - | - | |||||
| Remunerações e Contingências | 8.361.7757.915 incc's | -0 incc's | 8.361.7757.915 incc's | 10.009.704 | - | 1.125.777924 incc's | 11,67% | 8.883.927 | ||
| Remunerações | 8.361.775 | - | 8.361.775 | 10.009.704 | - | 1.125.777 | 11,67% | 8.883.927 | ||
| Grupo | Orçamento c/ ME'S | Tendência | Desvio | Desvio X Mês Anterior |
||||||
|---|---|---|---|---|---|---|---|---|---|---|
| R$ Reajustado | % | Total | % | A Gastar Projetado |
Reajuste (R$) | Desvio (R$) | Total (R$) | % Base INCC |
||
| OBRA GERAL + TAXA ADM | 124.513.45299.890 incc's | 100% | 141.198.774113.021 incc's | 100% | 107.991.31184.986 incc's | 18.988.008 | 16.685.32213.130,86 incc's | 35.673.330 | 13,15% | 636.239389 incc's |
| OBRA GERAL | 109.974.69688.410 incc's | 88% | 126.660.019101.541 incc's | 90% | 94.578.33274.430 incc's | 16.576.346 | 16.685.32213.130,86 incc's | 33.261.668 | 14,85% | 636.239389 incc's |
| OBRA MALL + TAXA ADM | 48.026.20338.793 incc's | 39% | 55.703.57444.835 incc's | 39% | 39.706.76231.248 incc's | 7.044.956 | 7.677.3716.041,87 incc's | 14.722.327 | 15,57% | 870.810640 incc's |
| OBRA MALL | 43.497.15135.228 incc's | 35% | 51.174.52341.270 incc's | 36% | 35.177.71027.684 incc's | 6.281.223 | 7.677.3716.041,87 incc's | 13.958.595 | 17,15% | 870.810640 incc's |
| Custos Indiretos | 7.251.592 | 5,8% | 9.772.042 | 7,7% | 7.049.119 | 1.011.818 | 2.520.450 | 3.532.268 | 33,58% | 551.521 |
| Mov. Terra / Fundação / Contenção | 2.884.704 | 2,3% | 8.041.625 | 6,3% | 47.592 | - 109.699 | 5.156.921 | 5.047.222 | 143,18% | 311.468 |
| Shopping | 32.458.730 | 26,1% | 32.458.730 | 25,6% | 27.178.874 | 5.226.979 | - | 5.226.979 | 7.822 | |
| Custos Adicionais | 902.125 | 0,7% | 902.125 | 0,7% | 902.125 | 152.125 | - | 152.125 | - | |
| Gastos Não Apropriados | - | 0,0% | - | 0,0% | - | - | - | - | - | |
| Remunerações e Contingências | 4.529.0523.564 incc's | 4% | 4.529.0523.564 incc's | 3% | 4.529.0523.564 incc's | 763.733 | -0,00 incc's | 763.733 | 0,00% | -0 incc's |
| Remunerações | 4.529.052 | 3,6% | 4.529.052 | 3,6% | 4.529.052 | 763.733 | - | 763.733 | - | |
| OBRA TORRES + TAXA ADM | 76.487.24961.097 incc's | 61% | 85.495.20068.186 incc's | 61% | 68.284.54953.738 incc's | 11.943.052 | 9.007.9517.089,00 incc's | 20.951.002 | 11,60% | - 234.571-251 incc's |
| OBRA TORRES | 66.477.54553.182 incc's | 53% | 75.485.49660.271 incc's | 53% | 59.400.62246.747 incc's | 10.295.122 | 9.007.9517.089,00 incc's | 19.303.073 | 13,33% | - 234.571-251 incc's |
| Custos Indiretos | 9.906.686 | 8,0% | 11.736.181 | 9,3% | 7.461.556 | 1.371.266 | 1.829.496 | 3.200.762 | 17,82% | - 718.890 |
| Mov. Terra / Fundação / Contenção | 4.226.370 | 3,4% | 11.404.825 | 9,0% | 1.139.207 | 130.310 | 7.178.455 | 7.308.765 | 145,70% | 484.427 |
| Estrutura | 11.550.270 | 9,3% | 11.550.270 | 9,1% | 10.206.216 | 1.919.619 | - | 1.919.619 | - 108 | |
| Alvenaria/Fechamento | 2.970.272 | 2,4% | 2.970.272 | 2,3% | 2.970.105 | 500.876 | - | 500.876 | - | |
| Impermeabilização e Tratamentos | 738.106 | 0,6% | 738.106 | 0,6% | 720.455 | 124.197 | - | 124.197 | - | |
| Revestimentos Internos | 6.033.196 | 4,8% | 6.033.196 | 4,8% | 6.033.196 | 1.017.376 | - | 1.017.376 | - | |
| Revestimento Externo | 4.923.836 | 4,0% | 4.923.836 | 3,9% | 4.923.836 | 830.305 | - | 830.305 | - | |
| Esquadrias | 7.393.962 | 5,9% | 7.393.962 | 5,8% | 7.393.962 | 1.246.842 | - | 1.246.842 | - | |
| Pinturas | 990.941 | 0,8% | 990.941 | 0,8% | 990.941 | 167.102 | - | 167.102 | - | |
| Granitos e Pedras | 583.129 | 0,5% | 583.129 | 0,5% | 583.129 | 98.333 | - | 98.333 | - | |
| Instalações | 13.472.227 | 10,8% | 13.472.227 | 10,6% | 13.289.470 | 2.266.896 | - | 2.266.896 | - | |
| Serviços Complementares | 1.355.451 | 1,1% | 1.355.451 | 1,1% | 1.355.451 | 228.569 | - | 228.569 | - | |
| Custos Adicionais | 2.333.099 | 1,9% | 2.333.099 | 1,8% | 2.333.099 | 393.430 | - | 393.430 | - | |
| Gastos Não Apropriados | - | 0,0% | - | 0,0% | - | - | - | - | - | |
| Remunerações e Contingências | 10.009.7047.915 incc's | 8% | 10.009.7047.915 incc's | 7% | 8.883.9276.991 incc's | 1.647.929 | -0,00 incc's | 1.647.929 | 0,00% | -0 incc's |
| Remunerações | 10.009.704 | 8,0% | 10.009.704 | 7,9% | 8.883.927 | 1.647.929 | - | 1.647.929 | - | |
| Período | Valor Contratado Obra | Gastos Base Caixa | Saldo a Pagar Obra | |||||
|---|---|---|---|---|---|---|---|---|
| INCC | ME'S | Total INCC | R$ Reajustado | No Mês INCC | No Mês R$ | INCC | R$ Corrigido | |
| TOTAL = | 38.793 | - | 38.793 | 48.026.267 | 13.586 | 15.996.507 | 25.206 | 32.029.760 |
| PRÉ-OBRA | 38.793 | - | 38.793 | 44.254.938 | 1.734 | 1.880.934 | 37.058 | 40.493.071 |
| 1 · abr/24 | 38.793 | - | 38.793 | 42.487.143 | 339 | 371.293 | 36.719 | 40.234.917 |
| 2 · mai/24 | 38.793 | - | 38.793 | 42.694.645 | 697 | 767.252 | 36.023 | 39.675.167 |
| 3 · jun/24 | 38.793 | - | 38.793 | 43.036.790 | 473 | 525.300 | 35.550 | 39.492.012 |
| 4 · jul/24 | 38.793 | - | 38.793 | 43.319.057 | 203 | 227.619 | 35.347 | 39.546.659 |
| 5 · ago/24 | 38.793 | - | 38.793 | 43.604.975 | 282 | 318.134 | 35.064 | 39.514.443 |
| 6 · set/24 | 38.793 | - | 38.793 | 43.880.545 | 443 | 503.198 | 34.621 | 39.286.815 |
| 7 · out/24 | 38.793 | - | 38.793 | 44.109.838 | 263 | 299.797 | 34.358 | 39.216.311 |
| 8 · nov/24 | 38.793 | - | 38.793 | 44.376.870 | 348 | 400.271 | 34.010 | 39.083.072 |
| 9 · dez/24 | 38.793 | - | 38.793 | 44.531.784 | 293 | 338.297 | 33.717 | 38.899.690 |
| 10 · jan/25 | 38.793 | - | 38.793 | 44.727.712 | 276 | 319.584 | 33.441 | 38.776.033 |
| 11 · fev/25 | 38.793 | - | 38.793 | 45.048.076 | 398 | 464.861 | 33.043 | 38.631.536 |
| 12 · mar/25 | 38.793 | - | 38.793 | 45.202.025 | 282 | 330.537 | 32.762 | 38.454.948 |
| 13 · abr/25 | 38.793 | - | 38.793 | 45.353.090 | 311 | 366.672 | 32.451 | 38.239.341 |
| 14 · mai/25 | 38.793 | - | 38.793 | 45.550.260 | 279 | 330.017 | 32.172 | 38.106.493 |
| 15 · jun/25 | 38.793 | - | 38.793 | 45.771.121 | 470 | 559.447 | 31.702 | 37.767.907 |
| 16 · jul/25 | 38.793 | - | 38.793 | 46.030.509 | 441 | 528.394 | 31.262 | 37.498.902 |
| 17 · ago/25 | 38.793 | - | 38.793 | 46.373.202 | 472 | 570.777 | 30.790 | 37.270.817 |
| 18 · set/25 | 38.793 | - | 38.793 | 46.565.180 | 514 | 625.092 | 30.277 | 36.837.703 |
| 19 · out/25 | 38.793 | - | 38.793 | 46.626.974 | 523 | 637.501 | 29.754 | 36.261.996 |
| 20 · nov/25 | 38.793 | - | 38.793 | 46.734.355 | 735 | 898.429 | 29.019 | 35.470.947 |
| 21 · dez/25 | 38.793 | - | 38.793 | 46.829.448 | 780 | 955.922 | 28.239 | 34.610.120 |
| 22 · jan/26 | 38.793 | - | 38.793 | 46.900.836 | 702 | 861.852 | 27.537 | 33.819.655 |
| 23 · fev/26 | 38.793 | - | 38.793 | 47.145.225 | 568 | 702.894 | 26.969 | 33.361.150 |
| 24 · mar/26 | 38.793 | - | 38.793 | 47.238.132 | 423 | 524.862 | 26.546 | 32.929.195 |
| 25 · abr/26 | 38.793 | - | 38.793 | 47.415.987 | 432 | 538.547 | 26.114 | 32.568.503 |
| 26 · mai/26 | 38.793 | - | 38.793 | 47.741.651 | 340 | 428.586 | 25.773 | 32.465.580 |
| 27 · jun/26 | 38.793 | - | 38.793 | 48.026.267 | 567 | 720.437 | 25.206 | 32.029.760 |
| Grupo | Orçamento Base | ME'S | Orçamento c/ ME'S | Gastos Caixa | % Base INCC | Avanço Físico com D.I. | Variação do Custo | Saldo Contratual Corrigido | ||
|---|---|---|---|---|---|---|---|---|---|---|
| R$ - I0 | R$ Reajustado | No Mês | Acumulado | |||||||
| OBRA GERAL + TAXA ADM | 105.525.44499.890 incc's | -0 incc's | 105.525.44499.890 incc's | 124.513.452 | 1.041.913 | 33.207.46328.035 incc's | 28,07% | 91.305.988 | ||
| OBRA GERAL | 93.398.35188.410 incc's | -0 incc's | 93.398.35188.410 incc's | 109.974.696 | 1.041.913 | 32.081.68727.111 incc's | 30,66% | 15,67% | −15,00% | 77.893.010 |
| OBRA MALL + TAXA ADM | 40.981.24738.793 incc's | -0 incc's | 40.981.24738.793 incc's | 48.026.203 | 720.437 | 15.996.81213.586 incc's | 35,02% | 32.029.391 | ||
| OBRA MALL | 37.215.92835.228 incc's | -0 incc's | 37.215.92835.228 incc's | 35.898.147 | 720.437 | 15.996.81213.586 incc's | 38,57% | 21,33% | −17,24% | 27.500.339 |
| Custos Indiretos | 6.239.774 | - | 6.239.774 | 7.251.592 | 92.311 | 2.722.923 | 39,66% | 23,20% | −16,46% | 4.528.668 |
| Mov. Terra / Fundação / Contenção | 2.994.403 | - | 2.994.403 | 2.884.704 | 233.942 | 7.994.033 | 241,86% | 97,06% | −144,79% | - 5.109.329 |
| Shopping | 27.231.751 | - | 27.231.751 | 32.458.730 | 394.184 | 5.279.856 | 17,02% | 13,16% | −3,87% | 27.178.874 |
| Custos Adicionais | 750.000 | - | 750.000 | 902.125 | 902.125 | |||||
| Gastos Não Apropriados | - | - | - | - | - | |||||
| Remunerações e Contingências | 3.765.3193.564 incc's | -0 incc's | 3.765.3193.564 incc's | 4.529.052 | - | -0 incc's | 4.529.052 | |||
| Remunerações | 3.765.319 | - | 3.765.319 | 4.529.052 | 4.529.052 | |||||
| OBRA TORRES + TAXA ADM | 64.544.19761.097 incc's | -0 incc's | 64.544.19761.097 incc's | 76.487.249 | 321.476 | 17.210.65114.448 incc's | 23,65% | 59.276.598 | ||
| OBRA TORRES | 56.182.42353.182 incc's | -0 incc's | 56.182.42353.182 incc's | 66.477.545 | 321.476 | 16.084.87413.524 incc's | 25,43% | 11,92% | −13,51% | 50.392.671 |
| Custos Indiretos | 8.535.420 | - | 8.535.420 | 9.906.686 | 115.028 | 4.274.626 | 45,14% | 23,20% | −21,94% | 5.632.060 |
| Mov. Terra / Fundação / Contenção | 4.096.061 | - | 4.096.061 | 4.226.370 | 127.434 | 10.265.619 | 222,58% | 97,06% | −125,51% | - 6.039.249 |
| Estrutura | 9.630.651 | - | 9.630.651 | 11.550.270 | 78.846 | 1.344.054 | 11,89% | −11,89% | 10.206.216 | |
| Alvenaria/Fechamento | 2.469.396 | - | 2.469.396 | 2.970.272 | 168 | 168 | 0,01% | −0,01% | 2.970.105 | |
| Impermeabilização e Tratamentos | 613.909 | - | 613.909 | 738.106 | - | 17.651 | 2,43% | −2,43% | 720.455 | |
| Revestimentos Internos | 5.015.819 | - | 5.015.819 | 6.033.196 | 6.033.196 | |||||
| Revestimento Externo | 4.093.531 | - | 4.093.531 | 4.923.836 | 4.923.836 | |||||
| Esquadrias | 6.147.120 | - | 6.147.120 | 7.393.962 | 7.393.962 | |||||
| Pinturas | 823.839 | - | 823.839 | 990.941 | 990.941 | |||||
| Granitos e Pedras | 484.796 | - | 484.796 | 583.129 | 583.129 | |||||
| Instalações | 11.205.331 | - | 11.205.331 | 13.472.227 | - | 182.758 | 1,40% | 0,56% | −0,84% | 13.289.470 |
| Serviços Complementares | 1.126.882 | - | 1.126.882 | 1.355.451 | 1.355.451 | |||||
| Custos Adicionais | 1.939.669 | - | 1.939.669 | 2.333.099 | 2.333.099 | |||||
| Gastos Não Apropriados | - | - | - | - | - | |||||
| Remunerações e Contingências | 8.361.7757.915 incc's | -0 incc's | 8.361.7757.915 incc's | 10.009.704 | - | 1.125.777924 incc's | 11,67% | 8.883.927 | ||
| Remunerações | 8.361.775 | - | 8.361.775 | 10.009.704 | - | 1.125.777 | 11,67% | 8.883.927 | ||
| Orçamento Rateado | Gastos Caixa Rateado | Valor de Rateio a Ajustar com o % de Rateio Acordado |
|||||||
|---|---|---|---|---|---|---|---|---|---|
| R$ | INCC | % de Rateio sobre o Total |
R$ (Acum.) | INCC (Acum.) | % sobre Gasto Total |
R$ | Gasto Total Ajustado | % sobre Gasto Total Ajustado |
|
| OBRA MALL + TORRES (SEM TAXA) | 37.245.316 | 35.256 | 39,9% | 15.996.016 | 13.586 | 49,86% | - 939.781 | 15.056.235 | 46,93% |
| Custos Indiretos | 5.587.347 | 5.289 | 37,8% | 2.722.923 | 2.343 | 38,91% | - 459.875 | 2.263.049 | 32,34% |
| Projetos, Ensaios, Consultorias e Taxas | 875.768 | 829 | 45,5% | 836.498 | 739 | 38,57% | - 28.628 | 807.871 | 37,25% |
| Administração Local da Obra | 1.870.404 | 1.771 | 36,4% | 1.094.015 | 927 | 45,98% | - 287.354 | 806.661 | 33,91% |
| Equipamentos | 1.038.154 | 983 | 45,0% | 196.547 | 163 | 17,99% | - 302 | 196.245 | 17,96% |
| Segurança e Saúde Ocupacional | 659.433 | 624 | 33,3% | 83.408 | 69 | 47,30% | - 24.634 | 58.774 | 33,33% |
| Consumos | 1.043.450 | 988 | 33,3% | 150.650 | 128 | 42,47% | - 32.418 | 118.232 | 33,33% |
| Serviços Preliminares | 100.137 | 95 | 33,3% | 361.804 | 316 | 43,81% | - 86.538 | 275.266 | 33,33% |
| Geral | 3.138.756 | 2.971 | 44,3% | 7.993.237 | 6.855 | 43,78% | - 479.906 | 7.513.330 | 41,15% |
| Movimento de Terra | 41.866 | 40 | 45,0% | 63.350 | 54 | 34,16% | - | 63.350 | 34,16% |
| Fundação, Contenção e Melhoramento | 3.096.890 | 2.932 | 44,3% | 7.929.887 | 6.801 | 43,88% | - 479.906 | 7.449.981 | 41,22% |
| Shopping | 27.231.751 | 25.777 | 100,0% | 5.279.856 | 4.388 | 100,00% | - | 5.279.856 | 100,00% |
| Lazer | 537.463 | 509 | 12,6% | - | - | - | - | ||
| Residencial | - | - | 0,0% | - | - | 0,00% | - | - | 0,00% |
| Hotel | - | - | 0,0% | - | - | 0,00% | - | - | 0,00% |
| Custos Adicionais | 750.000 | 710 | 27,9% | - | - | - | - | ||
| Gastos Não Apropriados | - | - | 0,0% | - | - | - | - | ||
| Orçamento Rateado | Gastos Caixa Rateado | Valor de Rateio a Ajustar com o % de Rateio Acordado |
|||||||
|---|---|---|---|---|---|---|---|---|---|
| R$ | INCC | % de Rateio sobre o Total |
R$ (Acum.) | INCC (Acum.) | % sobre Gasto Total |
R$ | Gasto Total Ajustado | % sobre Gasto Total Ajustado |
|
| OBRA MALL + TORRES (SEM TAXA) | 56.153.034 | 53.154 | 60,1% | 16.084.874 | 13.524 | 49,89% | 939.781 | 17.024.655 | 53,07% |
| Custos Indiretos | 9.187.847 | 8.697 | 62,2% | 4.274.626 | 3.647 | 60,89% | 459.875 | 4.734.500 | 67,66% |
| Projetos, Ensaios, Consultorias e Taxas | 1.050.438 | 994 | 54,5% | 1.332.288 | 1.172 | 61,30% | 28.628 | 1.360.916 | 62,75% |
| Administração Local da Obra | 3.261.972 | 3.088 | 63,6% | 1.285.159 | 1.096 | 54,16% | 287.354 | 1.572.513 | 66,09% |
| Equipamentos | 1.268.856 | 1.201 | 55,0% | 896.089 | 726 | 81,65% | 302 | 896.391 | 82,04% |
| Segurança e Saúde Ocupacional | 1.319.064 | 1.249 | 66,7% | 92.932 | 77 | 52,79% | 24.634 | 117.566 | 66,67% |
| Consumos | 2.087.212 | 1.976 | 66,7% | 204.082 | 174 | 57,57% | 32.418 | 236.500 | 66,67% |
| Serviços Preliminares | 200.305 | 190 | 66,7% | 464.076 | 403 | 56,08% | 86.538 | 550.614 | 66,67% |
| Geral | 3.951.708 | 3.741 | 55,7% | 10.265.619 | 8.630 | 55,73% | 479.906 | 10.745.525 | 58,85% |
| Movimento de Terra | 51.170 | 48 | 55,0% | 122.100 | 101 | 65,43% | - | 122.100 | 65,84% |
| Fundação, Contenção e Melhoramento | 3.900.538 | 3.692 | 55,7% | 10.143.519 | 8.529 | 55,63% | 479.906 | 10.623.425 | 58,78% |
| Shopping | - | - | 0,0% | - | - | 0,00% | - | - | 0,00% |
| Lazer | 3.736.433 | 3.537 | 87,4% | - | - | - | - | ||
| Residencial | 17.649.742 | 16.707 | 100,0% | 1.136.735 | 916 | 100,00% | - | 1.136.735 | 100,00% |
| Hotel | 19.687.636 | 18.636 | 100,0% | 407.895 | 331 | 100,00% | - | 407.895 | 100,00% |
| Custos Adicionais | 1.939.669 | 1.836 | 72,1% | - | - | - | - | ||
| Gastos Não Apropriados | - | - | 0,0% | - | - | - | - | ||
| Grupo | Orçamento c/ ME'S | Tendência | Desvio | Desvio X Mês Anterior |
||||||
|---|---|---|---|---|---|---|---|---|---|---|
| R$ Reajustado | % | Total | % | A Gastar Projetado |
Reajuste (R$) | Desvio (R$) | Total (R$) | % Base INCC |
||
| OBRA GERAL + TAXA ADM | 124.513.45299.890 incc's | 100% | 141.198.774113.021 incc's | 100% | 107.991.31184.986 incc's | 18.988.008 | 16.685.32213.130,86 incc's | 35.673.330 | 13,15% | 636.239389 incc's |
| OBRA GERAL | 109.974.69688.410 incc's | 88% | 126.660.019101.541 incc's | 90% | 94.578.33274.430 incc's | 16.576.346 | 16.685.32213.130,86 incc's | 33.261.668 | 14,85% | 636.239389 incc's |
| OBRA MALL + TAXA ADM | 48.026.20338.793 incc's | 39% | 55.703.57444.835 incc's | 39% | 39.706.76231.248 incc's | 7.044.956 | 7.677.3716.041,87 incc's | 14.722.327 | 15,57% | 870.810640 incc's |
| OBRA MALL | 43.497.15135.228 incc's | 35% | 51.174.52341.270 incc's | 36% | 35.177.71027.684 incc's | 6.281.223 | 7.677.3716.041,87 incc's | 13.958.595 | 17,15% | 870.810640 incc's |
| Custos Indiretos | 7.251.592 | 5,8% | 9.772.042 | 7,7% | 7.049.119 | 1.011.818 | 2.520.450 | 3.532.268 | 33,58% | 551.521 |
| Mov. Terra / Fundação / Contenção | 2.884.704 | 2,3% | 8.041.625 | 6,3% | 47.592 | - 109.699 | 5.156.921 | 5.047.222 | 143,18% | 311.468 |
| Shopping | 32.458.730 | 26,1% | 32.458.730 | 25,6% | 27.178.874 | 5.226.979 | - | 5.226.979 | 7.822 | |
| Custos Adicionais | 902.125 | 0,7% | 902.125 | 0,7% | 902.125 | 152.125 | - | 152.125 | - | |
| Gastos Não Apropriados | - | 0,0% | - | 0,0% | - | - | - | - | - | |
| Remunerações e Contingências | 4.529.0523.564 incc's | 4% | 4.529.0523.564 incc's | 3% | 4.529.0523.564 incc's | 763.733 | -0,00 incc's | 763.733 | 0,00% | -0 incc's |
| Remunerações | 4.529.052 | 3,6% | 4.529.052 | 3,6% | 4.529.052 | 763.733 | - | 763.733 | - | |
| OBRA TORRES + TAXA ADM | 76.487.24961.097 incc's | 61% | 85.495.20068.186 incc's | 61% | 68.284.54953.738 incc's | 11.943.052 | 9.007.9517.089,00 incc's | 20.951.002 | 11,60% | - 234.571-251 incc's |
| OBRA TORRES | 66.477.54553.182 incc's | 53% | 75.485.49660.271 incc's | 53% | 59.400.62246.747 incc's | 10.295.122 | 9.007.9517.089,00 incc's | 19.303.073 | 13,33% | - 234.571-251 incc's |
| Custos Indiretos | 9.906.686 | 8,0% | 11.736.181 | 9,3% | 7.461.556 | 1.371.266 | 1.829.496 | 3.200.762 | 17,82% | - 718.890 |
| Mov. Terra / Fundação / Contenção | 4.226.370 | 3,4% | 11.404.825 | 9,0% | 1.139.207 | 130.310 | 7.178.455 | 7.308.765 | 145,70% | 484.427 |
| Estrutura | 11.550.270 | 9,3% | 11.550.270 | 9,1% | 10.206.216 | 1.919.619 | - | 1.919.619 | - 108 | |
| Alvenaria/Fechamento | 2.970.272 | 2,4% | 2.970.272 | 2,3% | 2.970.105 | 500.876 | - | 500.876 | - | |
| Impermeabilização e Tratamentos | 738.106 | 0,6% | 738.106 | 0,6% | 720.455 | 124.197 | - | 124.197 | - | |
| Revestimentos Internos | 6.033.196 | 4,8% | 6.033.196 | 4,8% | 6.033.196 | 1.017.376 | - | 1.017.376 | - | |
| Revestimento Externo | 4.923.836 | 4,0% | 4.923.836 | 3,9% | 4.923.836 | 830.305 | - | 830.305 | - | |
| Esquadrias | 7.393.962 | 5,9% | 7.393.962 | 5,8% | 7.393.962 | 1.246.842 | - | 1.246.842 | - | |
| Pinturas | 990.941 | 0,8% | 990.941 | 0,8% | 990.941 | 167.102 | - | 167.102 | - | |
| Granitos e Pedras | 583.129 | 0,5% | 583.129 | 0,5% | 583.129 | 98.333 | - | 98.333 | - | |
| Instalações | 13.472.227 | 10,8% | 13.472.227 | 10,6% | 13.289.470 | 2.266.896 | - | 2.266.896 | - | |
| Serviços Complementares | 1.355.451 | 1,1% | 1.355.451 | 1,1% | 1.355.451 | 228.569 | - | 228.569 | - | |
| Custos Adicionais | 2.333.099 | 1,9% | 2.333.099 | 1,8% | 2.333.099 | 393.430 | - | 393.430 | - | |
| Gastos Não Apropriados | - | 0,0% | - | 0,0% | - | - | - | - | - | |
| Remunerações e Contingências | 10.009.7047.915 incc's | 8% | 10.009.7047.915 incc's | 7% | 8.883.9276.991 incc's | 1.647.929 | -0,00 incc's | 1.647.929 | 0,00% | -0 incc's |
| Remunerações | 10.009.704 | 8,0% | 10.009.704 | 7,9% | 8.883.927 | 1.647.929 | - | 1.647.929 | - | |
| Mês | Previsão Construtora (R$) | Gasto Caixa (R$) | Desvio · Meta ± 5,00% | |
|---|---|---|---|---|
| R$ | % | |||
| dez/24 | NÃO INFORMADO | 598.394 | — | — |
| jan/25 | NÃO INFORMADO | 536.304 | — | — |
| fev/25 | NÃO INFORMADO | 718.263 | — | — |
| mar/25 | NÃO INFORMADO | 515.011 | — | — |
| abr/25 | NÃO INFORMADO | 547.388 | — | — |
| mai/25 | NÃO INFORMADO | 1.325.426 | — | — |
| jun/25 | NÃO INFORMADO | 1.242.728 | — | — |
| jul/25 | NÃO INFORMADO | 2.114.107 | — | — |
| ago/25 | NÃO INFORMADO | 1.617.477 | — | — |
| set/25 | NÃO INFORMADO | 1.600.309 | — | — |
| out/25 | NÃO INFORMADO | 1.485.356 | — | — |
| nov/25 | NÃO INFORMADO | 1.597.339 | — | — |
| dez/25 | NÃO INFORMADO | 2.069.008 | — | — |
| jan/26 | NÃO INFORMADO | 1.735.670 | — | — |
| fev/26 | NÃO INFORMADO | 1.345.031 | — | — |
| mar/26 | NÃO INFORMADO | 1.169.358 | — | — |
| abr/26 | NÃO INFORMADO | 2.071.282 | — | — |
| mai/26 | NÃO INFORMADO | 893.773 | — | — |
| jun/26 | NÃO INFORMADO | 1.041.913 | — | — |